Approach
- The item definition
- The over-arching safety plan to be used during the development
- Hazard analysis and risk assessment
- Development of the safety goals and the specification of the functional safety concept
- Further iteration to technical safety requirements level
Situation and objective
- Tier 1 core development programme fornewhybrid brake booster
- HORIBA MIRA team responsibility for concept phase, technical safety requirements and safety analysis (ISO 26262)
Results and Benefits
- HORIBA MIRA’s adoption of industry standard analysis tools (Fault Tree + IQ-FMEA) ensured a seamless transfer of the safety analysis results