Approach

  • The item definition
  • The over-arching safety plan to be used during the development
  • Hazard analysis and risk assessment
  • Development of the safety goals and the specification of the functional safety concept
  • Further iteration to technical safety requirements level

Situation and objective

  • Tier 1 core development programme fornewhybrid brake booster
  • HORIBA MIRA team responsibility for concept phase, technical safety requirements and safety analysis (ISO 26262)

Results and Benefits

  • HORIBA MIRA’s adoption of industry standard analysis tools (Fault Tree + IQ-FMEA) ensured a seamless transfer of the safety analysis results